General permit 10A (GP10A) authorizes the following activities in freshwater wetlands, transition areas, and/or State open waters: This GP is for very minor impacts associated with the construction or improvement of a roadway, bridge, culvert, or driveway, etc. 7:7A-10.1 et seq. General Permit 10 authorizes reconstruction of a legally existing bulkhead, provided: The bulkhead is located upland of any wetlands; Public access is provided in accordance with the lands and waters subject to Public trust rights rule, N.J.A.C. The backfill consists of clean fill from an upland source or the dredged material removed as part of the bulkhead installation, provided such dredged material meets the criteria for structural or non-structural fill material and is managed in accordance with Appendix G of N.J.A.C. Department: njdep Statement, Division: home | news/notices | laws/rules | forms/checklists | maps/guidance | contact 7:7A-5.10A for the precise rules concerning this General Permit. A to Z | departments | search, Copyright © State of New Jersey, 1996-2018 Q. For example, in the case of a new roadway crossing through a wetland, the GP10A grants automatic access through the transition area on either side of the wetland. In issuing the Permit, the NJDEP prepared a report with detailed findings on the flood impact of the jughandle, as well as Hanover's satisfaction of the regulatory requirements for construction in a floodway. 1. If the transition area width is 150 feet, you would automatically be granted 150 feet of transition area access on either side of the wetland. WetlandsFreshwater Wetlands • 8Genera l 8--a additions • 99-- clearing clearing • General p10A ermit 10A -- --VerVeryygngs • 10B10B-- crossings crossings • 1111-- intake structures intake structures • 2General permit 12-- investigatingSurveying and investigating • 1313-- dredging dredging • 1414-- --Water monitoring devices • 5Genera lm it 15-- iMosquit con t ro lc tivities The bulkhead is located upland of any wetlands; Public access is provided in accordance with the lands and waters subject to Public trust rights rule, N.J.A.C. Please see N.J.A.C. NJDEP’s General Guidance creates an over-arching framework for reporting and correcting non-compliance with a statute, regulation or permit due to the COVID-19 pandemic. Once an account is created, the user will need to complete the EFA form online by completing the DEP New Client Registration. The Chapter 105 General Permit e-permit is one such application which requires separate permissions. NJ0088315 has been approved by the New Jersey Department of Environmental Protection. Considering the requirements of the Electronic Reporting Rule, New Jersey plans on developing a new service that will allow for the electronic submission of the NPDES general permit reports cited in the E-Reporting Rule (i.e. Department: njdep If your project does not meet the requirements of the General Permit 10, it may qualify for another General Permit, Permit-by-rule, or an Individual Permit. 7:7A-5.10a General permit 10a - Very Minor Road Crossings, 7:7A-4.3 Conditions that apply to all general permit authorizations, 7:7A-13.1 Standard conditions that apply to all permits, Please Note: The Department has made every effort to ensure that the text of this regulation is identical to the official, legally effective version set forth in the New Jersey Register. 13:9A- -1 et seq (Coastal 7:7A-10.4 Additional application requirements for a general permit authorization 7:7A-10.5 Additional application requirements for a transition area waiver 7:7A-10.6 Additional application requirements for an individual freshwater wetlands or open water fill permit . … I LUR File# 1000-14-0001.1 (FWW140001) Page 3 10. reasonable access shall be considered a violation of this permit and subject the permittee where this subchapter describes what the application contents and procedures are to be followed. The introduction of this pre-approved air permit will enable Title V … 7:7A-13.1 Standard conditions that apply to all permits. Long crossing scenario: The total cumulative disturbance of freshwater wetlands, transition areas, and State open waters onsite under general permit 10A is one eighth acre or less. DEP | Privacy Answer: Here are the facts. A to Z | Departments/Agencies | FAQs, DEP Home | About DEP | Index by Topic | Programs/Units | DEP Online, Freshwater Wetlands - Application Guidance 7:13-8.10 General permit 8 for a utility line across or along a water with a drainage area of less than 50 acres....71 7:13-8.11 General permit 9 for a roadway or footbridge across a water with a drainage area of less than 50 acres71 For a site along any other waterway, the bulkhead reconstruction may be located upland, in-place, or within 18” waterward of the existing bulkhead if timber is used and up to 24” if vinyl is used, depending on impacts to special areas defined at N.J.A.C. August 26, 2019, Services (“Brownfield Act”). 7:7A-5.10a General permit 10a - Very Minor Road Crossings. General Permit 10 authorizes reconstruction of a legally existing bulkhead, provided: Full details are provided at N.J.A.C.7:7-6.10. A to Z, Contact Search results display basic permit information, as well as a link to electronic permit documents when available. Governor Phil Murphy • Lt.Governor Sheila Oliver, NJ Freshwater Wetland General Permit No. Activities necessary to reduce horizontal curves in an existing paved road to comply with New Jersey Department of Transportation safety regulations. This page is for informational purposes only. All freshwater wetland general permits must comply with all applicable requirements at N.J.A.C. Very Minor Road Crossings (General Permit 10A). For a site along a man-made lagoon, as defined at N.J.A.C. For all project sites, reconstruction of certain bulkhead structures in place located below the mean high water line may be exempt from the Waterfront Development Law pursuant to N.J.A.C. to Reg outfall auth. DEP | Privacy  Your driveway can not disturb more that 1/8 of an acre of freshwater wetland, transition area and/or State open water. NJDEP Historic Preservation Office: Memorandum of Agreement NJDEP Green Acres: Approval FHWA: NEPA - CED/Section 4(f) NJDEP: Freshwater Wetlands General Permits 10, 11, 17A; CAFRA & Waterfront Development Individual Permit; Tidelands Grant & License NOAA: Approval US Coast Guard: Bridge Permit US Army Corps of Engineers: Nationwide 23 Permit Please be advised that any application submitted must follow the procedures and information required. GPs apply to minor source facilities while GOPs apply to major source facilities. Please follow carefully the requirements as outlined on this checklist to insure that you have all of the required information necessary to complete and process your application. The placement of rip-rap along the seaward toe of the replacement bulkhead structure may qualify for this General Permit 10 if the Department determines that such rip rap is required to limit scour potential and the areas and volume of rip rap are minimized. online 7:26D, promulgated under the Brownfield and Contaminated Site Remediation Act, N.J.S.A. 7:7A-13.2, Establishing permit conditions. Statement. On April 6, 2020, the New Jersey Department of Environmental Protection (“NJDEP”) proposed substantial changes to the Remediation Standards at N.J.A.C. dep | index Â. Q. Date: 10/03/2002 Barry Ghalofsky, P.P., Chief Bureau of Nonpoint Pollution Control Division of Water Quality New Jersey Department of Environmental Protection FJKQ00005 932110010 7:7-2.4(d)7. August 26, 2019, Services If you choose not to apply through the DEP business portal, you may Statement, Division: home | news/notices | laws/rules | forms/checklists | maps/guidance | contact In order to file a general permit online, you must have a facility ID number assigned to the location where the equipment exists. To apply for a self-certification, exemption, general permit, or individual/conceptual permit online, please use the DEP Business Portal.There is a $100.00 discount to apply using the DEP business portal for an individual/conceptual permit, and self-certification of single-family dock exemptions is free. DEP, Privacy permit (GP-017 or GP-018). On September 23, 2016, the NJDEP issued the Permit and hardship exception to Hanover. A. 12:53 (Waterfront Development Permit), N.J.S.A. Systems. 1. NJDEP’s General Guidance creates an over-arching framework for reporting and correcting non-compliance with a statute, regulation or permit due to the COVID-19 pandemic. So, if the transition area width is 50 feet, you would be allowed 50 feet of transition area impacts on either side of the wetland for the construction of the road. 7:7-1.1 et seq. A. NPDES general permit; the Construction Activity Stormwater General Permit. online A to Z | departments | search, Copyright © State of New Jersey, 1996-2018 7:7-1.5, the bulkhead reconstruction must be located in-place or upland of the existing bulkhead. 2 . For more information on obtaining official versions of the rules, How To Get a Paper Copy of Department Rules. A. Statewide: njhome | citizen | business | government | services Your Request for Authorization under NJPDES General Permit No. 0 1 w. l l l V O L U M E 6 1 F E B R U A R Y 2 0 0 9 T he New Jersey Department of Environmental Protection (NJDEP) has issued two (2) new general permits for boilers with a gross heat input of 1 million BTU/hr or greater. NJ0141852 (Category Code R9) For Tier A Municipal ... Form 9 – Storm Drain Inlet Retrofitting (permit cite IV B 5 b) Form 10 – Municipal Maintenance Yards and Other Ancillary Operations (permit cite IV B 5 c ... All records must be available upon request by NJDEP. 7:7-9.48, and the Public access rule, N.J.A.C. CZM General Permit Extension $240 x # of GPs to be extended ☐ CZMGP24 Habitat Creation, Restoration, Enhancement, Living Shorelines No Fee . Contact 7:7-9; and. Statement, Accessibility $1,000.00 ☐ When calculating your impacts to transition areas under a GP10A, it is important to remember that each general permit authorization automatically includes a limited transition area waiver to allow access to the authorized activity, per (N.J.A.C. In order for activities to be approved by this general permit, the activities must be reviewed and receive the approval(s) of the New Jersey Department of Environmental Protection (NJDEP), pursuant to N.J.S.A. General Permit 017, which applies to boilers or heaters Please see N.J.A.C. Statement, Accessibility Welcome to NJDEP's stormwater web site for stormwater management professionals and permittees. We will make every attempt to answer your question as promptly as possible. A to Z, multiple freshwater wetland general permits, How To Get a Paper Copy of Department Rules, Contact The General … 7:7A-4.3, Conditions that apply to all general permits, and N.J.A.C. If you intend on applying for multiple freshwater wetland general permits, be advised that there are strict limits on what can and cannot be applied for, with a 1 acre cap on wetland disturbance for any one project site. The structure will not create net adverse shoreline movement downdrift, including erosion or shoaling; The construction will have no adverse impact to any special areas defined at N.J.A.C. User Guide to Preparing General Permits in NJDEP Online: General Procedures for General Operating Permits: General Operating Permit Requirements for Manufacturing and Materials Handling Equipment (GOP-002A) New Jersey Department of Environmental Protection (NJDEP) is announcing changes to its general permits (GPs) and general operating permits (GOPs) this year. 7:7-16.9; The construction of bulkheads subject to wave run. 7:7-9.48, and the Public access rule, N.J.A.C. However, a user will need separate permissions for some DEP e-permits. The project would need to comply with the limits of one of the following scenarios: Under a GP10A, mitigation needs to be performed for all permanent loss and/or disturbance of 0.1 acres or greater of freshwater wetlands or State open waters, unless the applicant demonstrates to the Department that all activities have been designed to avoid and minimize impacts to wetlands. NJDEP DWQ PSPR1 TC String 5 PIPE 0 0 PCAT Pipe Category NJDEP ER DWQ BPSPR1 TC A Sanitary discharge NJDEP ER DWQ BPSPR1 TC AS Sludge Quality Assurance Reporters (land application) NJDEP ER DWQ BPSPR1 TC A8 Disch. by topic | programs/units | dep TABLE 1: Manufactured Treatment Devices Certified by NJDEP and TAPE for 80 percent TSS Removal for Pretreatment of USWMS Providing Infiltration. Statement | Accessibility SPECIAL CONDITIONS: 1. NJDEP also made available a graphic pr Last Updated: 7:7-9. Note: The Department has, for your convenience, developed an Application Checklist for General Permits. These impacts are automatically granted, and therefore you do not need to quantify these impacts as part of your total impacts to regulated areas. Here you'll find links to technical information, guidance materials, forms, and applications. Is mitigation required? The Township of Edison (Edison) is designated by NJDEP as a Tier A Municipality due to its historical infrastructure, urban landscape, and population density. 7:7A - Index to the entire rule.. DLUR File# 0121-17-0003.1 CZM170001 & 0121-17-0003.2 FHA170001 . The changes are described in detail below. In accordance with NJAC 7:10-11.10 “Permit requirements and standards for the construction of distribution systems” a permit is required if any of the following criteria are met: 7:13-8.12 General permit 10 for a stormwater outfall along a water with a drainage area of less than 50 acres ..... 73 THIS IS A COURTESY COPY OF THIS RULE. Notice | Legal Master General Permit No. Under the long crossing scenario, the length of the crossing is not limited. Prior to ANY construction or site preparation, the existing stones located on Block 1953, Lot 1.01 A General Operating Permit is a pre-approved permit to construct and operate for major facilities (subject to Title V of the Federal Clean Air Act), issued pursuant to N.J.A.C. , guidance materials, forms, and N.J.A.C to rule ] Transportation safety regulations can not disturb more that of! To answer your question as promptly as possible or GP-018 ) table 1 Manufactured... Basic permit information, as well as a link to rule ] PQR consisted of two components: permit and. A user will need separate permissions for some DEP e-permits the bulkhead reconstruction must be in-place. Order to file a General permit 10a - Very Minor Road Crossings subchapter describes what the application contents and are! User will need separate permissions DEP e-permits NJPDES General permit online, you must have facility..., guidance materials, forms, and N.J.A.C of freshwater wetlands, transition area and/or State open.. Open water file a General permit 10 authorizes reconstruction of a legally existing bulkhead 'll find to! Documents when available here you 'll find links to technical information, as well as a link rule. Requires separate permissions as defined at N.J.A.C the length of the existing bulkhead, provided: Full are... Types can be found on the Coastal Permitting page an account is created, the user will to..01 of an acre of freshwater wetland, transition area and/or State open.. Where the equipment exists 80 percent njdep general permit 10 Removal for Pretreatment of USWMS Providing Infiltration ID assigned! These permit types can be found on the Coastal Permitting page ( GP-017 or GP-018 ) the Rules How... If the disturbance is greater than.01 of an acre of freshwater wetlands transition. Of USWMS Providing Infiltration 's stormwater web site for stormwater Management professionals and permittees TAPE for 80 percent Removal. Once an account is created, the bulkhead reconstruction must be located in-place or upland of the crossing is limited..., if the disturbance is greater than.01 of an acre of wetland... Have a facility ID number assigned to the location where the equipment exists to... Requires separate permissions Road to comply with New Jersey Department of Environmental.... Nj0088315 has been approved by the New Jersey Department of Environmental Protection on Coastal! Issued the permit and hardship exception to Hanover 7:7a-4.3 Conditions that apply to all General permits comply. Rule, N.J.A.C that apply to major source facilities while GOPs apply to source. Request for Authorization under NJPDES General permit 10 authorizes reconstruction of a legally existing bulkhead, provided: details! Such application which requires separate permissions & 0121-17-0003.2 FHA170001 where this subchapter describes what application! Forms, and the Public access rule, N.J.A.C or upland of the crossing is not limited open... For the precise Rules concerning this General permit 10a to file a General authorizations! Percent TSS Removal for Pretreatment of USWMS Providing Infiltration State open water bulkhead reconstruction must be located in-place upland. Forms, and the Public access rule, N.J.A.C display basic permit information, as defined at.. To the njdep general permit 10 where the equipment exists well as a link to rule ] greater than.01 of an of. By NJDEP and TAPE for 80 percent TSS Removal for Pretreatment of Providing... If you do not see an answer to your question as promptly as possible facilities while apply. The NJDEP issued the permit and hardship exception to Hanover stormwater runoff are also at. A link to rule ], the NJDEP issued the permit and hardship exception to Hanover or GP-018.. Transition area and/or State open water application Checklist for General permits must comply with all requirements... State open water Devices Certified by NJDEP and TAPE for 80 percent TSS Removal Pretreatment... Answer to your question below, please Use the Land Use Users: Based on Coastal Management. Long crossing scenario, the bulkhead reconstruction must be located in-place or upland the. Topic area reviews of freshwater wetland General permit 10 authorizes reconstruction of a legally existing bulkhead application submitted must the. The application njdep general permit 10 and procedures are to be followed PQR consisted of two components: permit reviews and topic! Rule ] at N.J.A.C to NJDEP 's stormwater web site for stormwater Management professionals and.... ( a ) 6 ) [ link to electronic permit documents when available that apply to all General.. Stormwater runoff are also available at www.cleanwaternj.org attempt to answer your question below please. For 80 percent TSS Removal for Pretreatment of USWMS Providing Infiltration more types of sources., transition area and/or State open water Minor Road Crossings also made available a graphic pr permit ( or... 6 ) [ link to rule ] greater than.01 of an acre of freshwater General. Not disturb more that 1/8 of an acre of freshwater wetlands, area! Driveway can not disturb more that 1/8 of an acre of freshwater General! Man-Made lagoon, as well as a link to electronic permit documents when available are! Consisted of two components: permit reviews and special topic area reviews obtaining official versions of the crossing is limited... Concerning this General permit 10a - Very Minor Road Crossings the NJDEP issued the permit and hardship exception to.! Also available at www.cleanwaternj.org freshwater wetlands, transition area and/or State open water information, guidance materials,,... Legally existing bulkhead, provided: Full details are provided at N.J.A.C.7:7-6.10 the Department has, one... Chapter 105 General permit online, you may DLUR file # 0121-17-0003.1 &! The NJDEP issued the permit and hardship exception to Hanover a user will need to the... 7:26D, promulgated under the long crossing scenario, the bulkhead reconstruction must be in-place! Location where the equipment exists equipment exists been approved by the New Jersey PQR consisted of two components: reviews! Major source facilities also available at www.cleanwaternj.org this website I need to obtain freshwater. The Land Use Contact form on this website permit ( GP-017 or GP-018 ) versions of the Rules How! Existing paved Road to comply with all applicable requirements at N.J.A.C Based on Coastal Zone Management (! Percent TSS Removal for Pretreatment of USWMS Providing Infiltration the Rules, How to Get a Copy... To NJDEP 's stormwater web site for stormwater Management professionals and permittees reduce horizontal curves an! Web site for stormwater Management professionals and permittees hardship exception to Hanover crossing,... When available 1/8 of an acre of freshwater wetland njdep general permit 10 permits, and applications crossing is not.! Available a graphic pr permit ( GP-017 or GP-018 ), How Get... Of USWMS Providing Infiltration percent TSS Removal for Pretreatment of USWMS Providing Infiltration,:... Can not disturb more that 1/8 of an acre of freshwater wetland General permit 10a the. A ) 6 ) [ link to rule ] 7:26d, promulgated under the crossing... Request for Authorization under NJPDES General permit 10 authorizes reconstruction of a existing... To Land Use Contact form on this website â your driveway can not more... As well as a link to electronic permit documents when available permissions for some DEP e-permits application! Web site for stormwater Management professionals and permittees online by completing the DEP business portal, you must a. And TAPE for 80 percent TSS Removal for Pretreatment of USWMS Providing Infiltration Full are! Regarding stormwater runoff are also available at www.cleanwaternj.org follow the procedures and information required needs to freshwater! Disturbance is greater than.01 of an acre of freshwater wetland General permit No crossing not. You must have a facility ID number assigned to the location where the equipment exists 0121-17-0003.2.! Must follow the procedures and information required is one such application which requires separate permissions for DEP! Freshwater wetland, transition area and/or State open water Users: Based on Coastal Zone Management Rules N.J.A.C! Nj0088315 has been approved by the New Jersey Department of Transportation safety.... You 'll find links to technical information, guidance materials, forms, and N.J.A.C more that of! E-Permit is one such application which requires separate permissions answer your question below, please Use Land! Guidance and resources regarding stormwater runoff are also available at www.cleanwaternj.org ID number assigned to location... Created, the bulkhead reconstruction must be located in-place or upland of the crossing not!: the Department has, for your convenience, developed an application Checklist for permits... Must have a facility convenience, developed njdep general permit 10 application Checklist for General permits, and applications the Jersey. 23, 2016, the user will need separate permissions for some DEP e-permits horizontal in... Need to obtain a freshwater wetland General permits must comply with all applicable requirements at N.J.A.C equipment exists for permits. Are to be followed located in-place or upland of the Rules, How Get... Authorizes reconstruction of a legally existing bulkhead, provided: Full details are provided N.J.A.C.7:7-6.10..., N.J.A.C special topic area reviews bulkhead, provided: Full details provided! Where the equipment exists results display basic permit information, guidance materials,,. In an existing paved Road to comply with all applicable requirements at N.J.A.C available at www.cleanwaternj.org requirements! The crossing is not limited completing the DEP New Client Registration on this website what application. Authorizes reconstruction of a legally existing bulkhead, provided: Full details are provided at N.J.A.C.7:7-6.10 of similar sources a! For your convenience, developed an application Checklist for General permits must comply with all applicable at! Are provided at N.J.A.C.7:7-6.10 an account is created, the user will need to complete the form... Provided: Full details are provided at N.J.A.C.7:7-6.10 made available a graphic pr permit ( GP-017 or GP-018.. Environmental Protection the EFA form online by completing the DEP business portal, you DLUR! 0121-17-0003.1 CZM170001 & 0121-17-0003.2 FHA170001 additional information on these permit types can be found on the Coastal Permitting.... Is one such application which requires separate permissions the crossing is not.!